Construction work progressing according to time-schedule
December 2009: The site activities is currently at its peak with some 1,100 people at the site, and approximately 80% of the construction works completed. The construction work is progressing according to time-schedule.

View of the CCGT plant from the south east of the site from the existing coal fired power stations land. The picture is dominated by the air cooled condenser (ACC) structure. To the left of the ACC is Unit 20 (HRSG, gas turbine and steam turbine). In the foreground the existing 132,000 Volt overhead lines can be seen which have been a challenge to work under during the construction period.

View inside the Unit 10 turbine building showing the gas turbine closest, generator in the middle and steam turbine the furthest away from the camera. Unit 10 will be the first unit to be put into service.

View from the top of HRSG of Unit 20 overlooking Unit 10. In the middle is the 'fin-fan' coolers which are used to cool water used in common processes. This view is directly south over the River Severn and England can be seen on the horizon.