Too windy
Gale force winds are not popular in Esbjerg these days! The erection of Horns Rev 2 is deeply dependent on weather conditions. Everyone is intent on getting as much work done as possible during the summer months – however, no one can control the weather.
The beginning of August has been very windy, so even though the work of securing the monopiles and laying the cables is progressing, Energinet.dk is waiting for better weather before they can erect the transformer platform offshore – 36 hours are all they need.