Home
  • Home
  • Sitemap
  • All DONG Energy sites
  • Dansk
  • News
  • About Horns Rev 2
  • Images
  • Contact Us
  • About DONG Energy
  • Horns Rev 2 News
News
The world’s largest offshore wind farm supplies its first power
Minor fire in condenser battery at transformer platform
First turbine erected at Horns Rev 2
The accommodation platform in deep water
422 tonnes dignified hoist from the quay went according to plan
Naming Ceremony
Layer cake and strawberry champagne on M7
Horns Rev 2 sends submarine cable towards the cost
No more foundations!
Installation of transformer completed
Transformer platform installed
Too windy
The Danish trade journal ’Ingeniøren’ brings article about Horns Rev 2
Successful maiden voyage!
Crown Prince Frederik of Denmark inaugurates Horns Rev 2
Print | Enlarge text
dongenergy.com

First turbine erected at Horns rev 2

Everyone was excited, vessels had been trimmed after the winter season, all turbine parts were ready at the port – the only thing missing was beautiful spring weather with a calm sea, a clear blue sky, and a bright sun. The fine weather arrived on 19 March 2009, and the first turbine was erected onto the world’s largest offshore wind farm.


The vessel Sea-Power hoists the rotor blades onto the turbine. Soon the first turbine is erected.


Later that evening, TV2 News broadcasted the national news.
 