Anholt News
19.05.2013
All turbines are erected at Anholt Offshore Wind Farm
On 19 May 2013, the installation vessel ‘Sea Power‘ erected turbine no. 111 at Anholt Offshore Wind Farm. Now all turbines are erected at the wind farm.
02.05.2013
Anholt Offshore Wind Farm – Newsletter, May 2013
At the end of April, 59 wind turbines had been connected to the grid. It corresponds to a total capacity of 212.4MW. This makes Anholt Offshore Wind Farm the largest offshore wind farm in Denmark.
03.04.2013
Anholt Offshore Wind Farm - Newsletter April 2013
At the end of March 2013, 75 wind turbines had been installed in Anholt Offshore Wind Farm; 68 are connected to the grid and 39 have produced electricity.
05.03.2013
Anholt Offshore Wind Farm - Newsletter - March 2013
At the end of February 2013, 48 wind turbines had been installed in Anholt Offshore Wind Farm; 44 are connected to the grid and 30 have produced electricity.
05.02.2013
Anholt Offshore Wind Farm - Newsletter - February 2013
A total of three installation vessels are now in operation to exploit the few and often short-term installation windows which the season allows.
14.01.2013
Anholt Offshore Wind Farm - Newsletter, January 2013
Since spring 2012, DONG Energy has systematically established the operations organisation which will take over operation and maintenance of Anholt Offshore Wind Farm.
07.12.2012
Anholt Offshore Wind Farm - Newsletter - December 2012
Already on 14 November 2012, Anholt Offshore Wind Farm sent its first production of more than 25MW to the Western Danish power grid
13.11.2012
Anholt Offshore Wind Farm - newsletter November 2012
Since the wind turbine installation started on 1 September 2012, bad weather has affected the area, causing a strong breeze and heavy sea. All weather windows enabling installation have been used optimally.
05.10.2012
Anholt Offshore Windfarm - Newsletter October 2012
First Power: On Friday 21 September at 11:00 a.m., the wind technicians could connect wind turbine A01 in Anholt Offshore Wind Farm to the Danish grid
21.09.2012
First power from Anholt offshore wind farm
Press release: The first turbine in the Anholt Offshore Wind Farm was installed on Monday 3 September and today, just under three weeks later, the first turbine has exported power into the Danish power grid.
31.08.2012
Anholt Offshore Wind Farm - Newsletter September 2012
The next phase of Anholt Offshore Wind Farm is waiting to take its start. Turbine installation will commence on 1 September 2012
01.08.2012
All foundations for Anholt Offshore Wind Farm are in place
The last of the 111 transition pieces has now been installed on monopile no. 111 in Anholt Offshore Wind Farm.
05.07.2012
Anholt Offshore Wind Farm - Newsletter July 2012
The exhibition on Anholt Offshore Wind Farm, DjursWindGlobe, officially opened on 25 June - DONG Energy’s Project Manager, Claus Bøjle Møller gives a status of the last six months.
07.06.2012
Anholt Offshore Wind Farm - Newsletter, June 2012
After many months of manufacturing and preparation, it is now time for the array cable installation to commence on the Anholt project.
03.05.2012
Anholt Offshore Wind Farm - Newsletter, May 2012
DONG Energy and the project organisation behind Anholt Offshore Wind Farm celebrated two important milestones on Friday 27 April 2012 when the operating and service compound in Grenaa was inaugurated and the wind farm's first service vessel was baptised.
04.04.2012
Anholt Offshore Wind Farm - Newsletter April 2012
As of 1 April 2012, 37½ of the 111 monopiles that make up Anholt Offshore Wind Farm are installed, and as such one third of the driving is complete.
05.03.2012
Anholt Offshore Wind Farm – Newsletter, March 2012
As of 1 march 2012, 22 monopiles have been installed. At the same day, the first 11 wind technicians started in Grenaa.
06.02.2012
Anholt Offshore Wind Farm - Newsletter, February 2012
Since the first monopile was installed at 19.00hrs on New Year’s Eve, periods of good weather have been used to install foundations. On 1 February 2012, Svanen had erected 14 monopiles.
05.01.2012
Anholt Offshore Wind Farm – Newsletter, January 2012
While others were about to enjoy their New Year’s Eve dinner, the installation vessel Svanen started the installation of the first monopile at Anholt Offshore Wind Farm.
05.12.2011
Anholt Offshore Wind Farm - Newsletter, December 2011
We are almost ready to start - the construction of Denmark’s largest offshore wind farm will soon begin
01.11.2011
Anholt Offshore Wind Farm - newsletter November 2011
Industrial network has ensured local orders for more than DKK 100 million kroner in connection with Anholt Offshore Wind Farm
20.10.2011
Divestment of stakes in Anholt offshore wind farm has been approved
DONG Energy - Company announcement
05.10.2011
Anholt Offshore Wind Farm – Newsletter, October 2011
Stone fishing and construction of the artificial reefs commenced in August, and at present, approximately 5-600 stones have been removed, and three artificial reefs have been constructed.
08.09.2011
Anholt Offshore Wind Farm – Newsletter no 4 September 2011
Production of the elements for Anholt Offshore Wind Farm is commencing
01.07.2011
Anholt Offshore Wind Farm - newsletter no 3, July 2011
Plans for establishing approximately 28 artificial reefs within the 88km2 wind farm area.
01.06.2011
Anholt Offshore Wind Farm - newsletter no. 2, June 2011
The commercial boat builder Hvide Sande Skibs- & Baadebyggeri to supply two service vessels for Anholt Offshore Wind Farm
03.05.2011
Anholt Offshore Wind farm - Newsletter no 1, May 2011
Subscribe to news on the Anholt Offshore Wind Farm
20.04.2011
The location of the wind turbines in Anholt Offshore Wind Farm is now final
The wind farm layout ensures the largest possible contribution to reduction of CO2 emissions, but the seabed conditions have played an important part
28.03.2011
PensionDanmark and PKA to become co-owners of Denmark's largest offshore wind farm
PensionDanmark, PKA and DONG Energy will hold a joint press conference about the agreement on: 25 March at 13.45
03.01.2011
The Anholt project sets up base at the Port of Grenaa
DONG Energy has purchased the domicile of the Port of Grenaa and two cold stores at the Port of Grenaa.
22.06.2010
DONG Energy to build Anholt offshore wind farm
Earlier today, the Danish Energy Agency awarded DONG Energy the concession to build the next major offshore wind farm in Denmark off the Danish island of Anholt in the Kattegat.
07.04.2010
DONG Energy submits tender for concession to build Anholt offshore wind farm
Earlier today, DONG Energy submitted a binding tender to the Danish Energy Agency for the concession to build a 400 MW offshore wind farm off the Danish island of Anholt in the Kattegat.