Project Programme
Phase 1 2008
Geotechnical investigations
2009
Tender, Planning and Design
2010
April - July: Foundation Installations
May - July: Offshore Substation Installation
June - August: Cable Installations
August - January (2011): Installation of Turbines
2011
Project Commissioning
Phase 22009
June - November: Geotechnical investigations
2009-2010
Tender, Planning and Design
2010
April - June: Offshore Substation Installation (part 1)
2011
April - June: Foundation Installations
April - June: Cable Installations
May - July: Offshore Substation Installation (part 2)
May - December: Installation of Turbines
2012
Project Commissioning