| 2008 |
|
| April |
Preparation of seabed |
| May |
Installation of foundations |
| July |
Internal cabling |
| August |
Installation of transformer platform |
| November |
Installation of accommodation platform |
| 2009 |
|
| March |
Commissioning of the turbines |
| May |
Commissioning |
| December |
Completion of the project |
| 2010 |
|
| January |
Final taking-over for commercial operation |